Crews were working in that area to replace storm water piping and manholes that were in the driving portion of the road. The majority of that work is now complete.
New manhole being installed |
Shown above is a new manhole that was installed and crews installing the new piping into the manhole. The manholes and piping that were removed were in fairly good shape for their age but the new stuff will ensure adequate performance moving forward. The older manhole in this section was made of brick and is shown below.
Old manhole made from bricks |
Pouring an intersection of sidewalk |
The two major parts of the new ADA requirements deal with the slope of the sidewalk and the notification domes at the intersections to the road. Below one of the staff from Smith Concrete works on placement of the dome sections along West 5th Street.
Installing the dome panels |
That's it for this post but check back soon as we will be adding some updated information on traffic closures as the project moves east down West 5th Street.