Meanwhile the prime contractor who will be removing the old asphalt and putting down the new lifts is starting to get ready to move in to Storm Lake for that phase of the work which will start again at the far west end of the project area in Stage A - west of Northwestern and 5th Street intersection. The process of removal could start as early as Thursday, July 24, 2014. Stage A is shown in the graphic below:
Stage A - Milling Schedule |
During the removal process the road will be open but movement of traffic will be slow. Following removal the project engineer will review the sub-base of the road and determine if there is any need for patching which will be completed prior to the actual final paving of the road. The road will be uneven and rough following removal and drivers should SLOW DOWN and use CAUTION.
The patching process may require areas where the road will be closed and/or one lane traffic for a few days while the repairs are made and the concrete cures.
During the ENTIRE removal process and immediately after (until the final pavement is placed) CITIZENS ARE ASKED TO REDUCE SPEEDS AND TAKE EXTRA PRECAUTIONS - including using alternative routes if possible when traveling in the construction area. You should EXPECT DELAYS during these phases if traveling on West 5th Street.
As close to the removal as possible (pending the number of patches that are required) the asphalt paving crew will be back to pave the road. During the paving process they will have the road closed to all traffic and traffic control will be present to reroute traffic.