Monday, August 11, 2014

August 11 Update

Here is the latest schedule as of this afternoon:

Sub-contractor will be patching areas on the section between Vestal Street and the RR tracks to the east today and tomorrow (August 12).

On Wednesday, August 13th the contractor will place the first lift of asphalt down on the section between the RR tracks and Vestal Street.

That work will be immediately followed by the placement of the second lift from Northwestern to the RR tracks.  Based on this schedule the section from Northwestern to the RR Tracks will be open on Friday, August 15th.

On Thursday, August 14th the contractor will start the milling and removal of asphalt from the section east of the RR tracks to Lake Avenue.  That work is anticipated to take two days followed by the required patching that is needed.

Later this week we will have a map available of the closures once work starts on the eastern most phase of the project so check back to the blog later this week to see that map.

Again once paving starts in the respective areas the road will be closed to all traffic in that section until the paving is complete.