August 15, 2014 Update

Rain, Rain, you know the rest!

The weather is impacting the progress of the project and at this point work is halted until at least Monday but the current forecast for Monday through Wednesday is not much better.  We'll update next Monday again if there are any further delays due to weather.

As of today here is the schedule moving forward:

Section from Northwestern to the RR Tracks -
Paving of the final lift of asphalt is currently scheduled for Monday, August 18th.  If we stay on that schedule the road will open to all traffic sometime on Tuesday, August 19th.

Section from the RR Tracks east to the alley between Ontario and Geneseo Streets -
Milling will occur on Monday, August 18th or the same day as the paving of the section from Northwestern to the RR Tracks.  This will close the section of road to through traffic.  Access to businesses and parking will be on side streets only.  Depending on the condition of the road cross traffic MAY be allowed on Ontario Street.

Patching of this section will immediately follow with paving of the first lift to follow that.  The second lift will be done in conjunction with the paving of the rest of the section east of the RR tracks.

Section from the alley between Ontario and Geneseo Streets to Lake Avenue -
As of right now it is anticipated that milling on this section will occur late next week or early the week of August 25th.  Patching and the first lift of paving will follow.

The map below shows the work sections for the downtown area.