We are ready to move east yet again as the contractor today starting placing the first lift of asphalt down on the section from Northwestern to Vestal Street. They hope to finish that lift yet today but if not they will most likely finish on Monday. Driving on the road while the lift is being put down and cooling is no allowed so residents will be asked to park on side streets for this section while this work is being done.
The contractor is ready to start the milling process on the next section from Vestal Street to the railroad tracks. They are scheduled to start the milling process on this section on Saturday, August 9th. Patching will follow immediately after they have finished the milling to be followed by the placement of asphalt in this section.
More information next week on the section east of the railroad tracks.