Tuesday, August 5, 2014

Stage A Almost Complete & Other Updates

The contractor was back onsite today placing asphalt in Stage A from Vista Drive to Northwestern.  That section should be finished up tonight and should be open to thru traffic yet today!

Work will not focus on the section from Northwestern to Vestal Street with potentially the start of paving in that are tomorrow (weather pending).  If we have rain tomorrow, which is highly predicted, it will push back the first lift to Thursday.  Once the first lift on this section has been placed the contractor will start removals in the next section from Vestal to the RR Tracks.  Once removals start there the section will be closed to through traffic and local traffic will have limited access until the paving starts which would currently be anticipated to be around Tuesday (August 12th) next week.